Brisbane International Cruise Terminal - first concrete pour for the terminal building slab

2,129 views · 10 likes · 0 comments · Jul 12, 2019 · 1:30 · Short length
Open on YouTube

Well, we’ve wrapped up another big week at the Brisbane International Cruise Terminal site. This was the first of eight sections – pouring the ground slab for the building is expected to take around 6-8 weeks to complete. The site’s changing daily now, and we look forward to keeping everyone up to date with its progress.